Skip to main content

Delhi builder ordered to return excess charges to elderly couple

A Delhi-based builder has been asked by the top consumer court to refund Rs 1.91 lakh charged in excess from an elderly couple, to whom the delivery of two flats in Gurgaon was delayed for 20 months on the ground that an electricity connection was lacking.

The delay by Today Homes Infrastructures amounted to deficiency in service, the National Consumer Disputes Redressal Commission said.

The national commission upheld the state commission's decision against the interest collected by the builder from the flat applicants, OP Ratra, 72, and his wife Harmeet, 68. Ratra and his wife booked two floors in the project of the builder's units bearing No 86 at the ground floor and the first floor, Blossom-II at Sector-51, Gurgaon. The two complainants totally paid Rs 66.88 lakh.

"In our observation, the builder claiming that he has right to charge interest at the rate of 15 percent per annum appears to be unjust and an exploitation of consumers. Hence, the builder charging interest of Rs 1.91 lakh was not proper and is an unfair trade practice," said commission Presiding Member JM Malik and Member SM Kantikar.

Hauling up Today Homes Infrastructures for delaying the delivery of possession of the flats by 20 months, the national commission said: "The complainants (couple) had paid the entire price of the units, the possession should be given with all amenities. The petitioner failed to do so, which is deficiency in service."

"The builder tried to cover up its deficiency by taking the plea that the delay was caused due to non-availability of the electricity by the electricity department and the possession could be taken without the electricity connection," the commission said.

"As the complainants are 72 and 68-year-old, the senior citizens suffered exploitation and inconvenience due to non-delivery of the flat within specified period of time and were made to run from pillar to post," the national commission said.

Upholding the state commission's decision against Today Homes Infrastructures, Malik said: "It is very clear from the documents on record that the (builder) had not given physical possession of the units to Ratra and his wife after 21 months from the date of agreement but the same was delivered after 41 months. Hence, the petitioner delayed the possession for 20 months. This is deficiency in service."

The builder was also pulled up for delay in filing the appeal in the national commission.

"We do not find any merit in this petition, as well there is unexplained delay of 87 days in filing this revision petition. There is no illegality in the order of state commission. Therefore, we dismiss this revision petition," Malik said.

The builder has the option of challenging the national consumer commission's decision in the Supreme Court.

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Court approached in the early stages of arbitration will prevail in all other subsequent proceedings

In National Highway Authority of India v. Hindustan Steelworks Construction Limited, the Hon'ble Delhi High Court opined that once the parties have approached a certain court for relief under Act at earlier stages of disputes then it is same court that, parties must return to for all other subsequent proceedings. Language of Section 42 of Act is categorical and brooks no exception. In fact, the language used has the effect of jurisdiction of all courts since it states that once an application has been made in Part I of the Act then ―that Court alone shall have jurisdiction over arbitral proceedings and all subsequent applications arising out of that agreement and arbitral proceedings shall be made in that Court and in no other Court. Court holds that NHAI in present case cannot take advantage of Section 14 of the Limitation Act, 1963 for explaining inordinate delay in filing present petition under Section 34 of this Act in this Court.

Procedure to be followed on admissibility of additional evidence at appeal stage

In The Corporation of Madras vs M. Parthasarathy & Ors., the trial court had allowed the respondent company to file evidence in the form of photocopies and had dismissed all the four suits filed by the respondents with costs as the evidence were in the form of photocopies and were objected to by the respondents. On appeal the Additional District Judge allowed the respondents to file additional evidence in the form the original documents of the earlier admitted photocopies and based on the same allowed the appeal. In its turn the High Court also dismissed the appeal filed by the appellants who in turn approached the Supreme Court. The Supreme Court decided that the first Appellate Court committed two jurisdictional errors in allowing the appeals.  Referring to earlier judgements of the Supreme Court in Land Acquisition Officer, City Improvement Trust Board vs. H. Narayanaiah & Ors., , Shalimar Chemical Works Ltd. vs. Surendra Oil & Dal Mills (Refineri...