Skip to main content

Power firms can't change meters unilaterally: HC

A power company cannot unilaterally change a consumer's electricity meter because it suspects the instrument is defective, the Bombay high court has ruledin an important order.

Putting the reins on power companies, Justice Ashok Bhangale, while hearing a two-decade-old case, said that if there was a dispute about the working of a meter, in the absence of allegations of fraud against the consumer, the matter has to be referred to the electricity inspector. Moreover, the inspector can decide on additional charges only for a period up to six months prior to when the dispute was raised.

"Provisions of the Indian Electricity Act manifest that the original correct meter once installed acquires a sacrosanct status. After installation, both parties cannot remove or replace the meter," said the judge.

The court said that if the power company or consumer suspects that a meter is defective, then the matter should be brought before the electricity inspector. The company will not be permitted to replace the meter until its correctness is decided by the officer.

"Doubts about a defective meter must be finally scrutinized and decided by the electrical inspector on a reference made to such authority. The board [Maharashtra State Electricity Board] should not be permitted to instal another meter simply by doubting the correctness of the earlier meter installed by it," said the judge. "Any proposal of substitution of one meter by another should not be permitted until the correctness of the installed meter is decided by electrical inspector as incorrect. Any liberty granted to the board to continue to dislodge and dislocate one meter after another meter unreasonably, arbitrarily , whimsically and without the concurrence of the consumer will encourage mischief and high-handedness of the board and such action is bound to seriously impair the rule of law between the parties."

The court was hearing a dispute that dates back to 1993, when the Maharashtra State Electricity Board (MSEB) issued a notice to Thane-based Hindustan Gas Industries Ltd (HGIL) asking it to pay additional charges as the meter was found to be slow and threatened to disconnect the power supply within 24 hours. HGIL challenged the letter, which was struck down by the civil court in 1999. MSEB challenged the order in the high court.

The court said that the law makes it clear that if a dispute is raised, the limit set is six months prior and the meter reading before that cut-off date is presumed to be correct.

Article referred: http://timesofindia.indiatimes.com/city/mumbai/Power-firms-cant-change-meters-unilaterally-HC/articleshow/22955002.cms

Comments

Most viewed this month

Merits and the terms of contract are irrelevant for invoking of the bank guarantees

In Sabarkantha Annuity Pvt. Ltd. Vs. NHAI and Ors, the Petitioner filed before the Delhi High Court  petition under Section 9 of the Arbitration and Conciliation (Amendment) Act, 2015 with a prayer that, Respondents be restrained from acting upon the letter dated 15th September, 2017 or from invoking the Bid securities of the Petitioner to the tune of Rs. 10.93 Crores and also restraining the banks from honouring the invocation of said bank guarantees on behalf of Respondent No. 1 acting in terms of letter dated 3rd November, 2007. Petitioner has relied upon Clauses Nos. 9.1.1, 9.1.2 and 4.3 of the agreement dated 28th April, 2017 entered into between the parties to say the claim for damages since is not a claim for a sum presently due and payable and the respondent would be entitled to damages only on proof of loss, per Clause 4.3 of the agreement and hence is not entitle to the entire sum of bid security.  The Court found that Clause No. 9.1.2 speaks of an exclusiv...

Right of pre-emption under West Bengal Land Reform Act

In Rabindra Nath Kundu & Anr vs Sudhir Hira, Bijoy Krishna Hira being the owner in the suit plot, gifted to Santosh Kumar Hira demarcated 11 decimals of land vide deed of gift dated 27.4.2004 and the latter sold 9 decimals out of 11 decimals of land to Sudhir Hira the preemptor/opposite party no. 1 and well demarcated 1.65 decimals of land in the said plot along with several other plots were sold, transferred and conveyed to the preemptees/petitioners herein by a registered deed of sale dated 10.8.2010, the subject matter of preemption. It is argued on behalf of the preemptees that  the present opposite party no. 1/preemptor Sudhir Hira has no relationship of co-sharership with Santosh Kumar Hira opposite party no. 2 as the demarcated portion of land has been purchased. It is settled principle of law that partial preemption is not permissible and this was what the view adopted by this Hon'ble High Court is Surendra Vs. Abhimannu reported in (1980) 1 Cal LJ 135 whe...

CBI has no jurisdiction to probe affairs of medical college:HC

The Madras High Court has quashed charges against administrators of a medical college and dismissed CBI's petitions opposing discharge of officials of two other medical colleges, saying the investigation agency, or any other external agency for that matter, has no jurisdiction to probe the affairs of a medical college. Quashing the charges against the administrators of a medical college and dismissing CBI's petitions opposing the discharge of officials of two other medical colleges, Justice Aruna Jagadeesan said "contravention of rules and regulations may be an offence against the statute but is not a crime. There is no room or jurisdiction for any external agency to investigate the affairs of any medical institution coming within the purview of the Medical Council of India." In identical set of orders, all delivered on August 6, Justice Jagadeesan said "the shortfall in faculties and submissions of fake/forged documents would only disentitle the institution...