Skip to main content

Supreme Court: Calculating damage in the absence of evidence

Extent of allowing stipulated liquidated damages by way of penalty in absence of evidence of actual loss, discussed

Supreme Court: Deciding the pivotal question as to when and to what extent can the stipulated liquidated damages for breach of a contract be held to be in the nature of penalty in absence of evidence of actual loss and to what extent the stipulation be taken to be the measure of compensation for the loss suffered even in absence of specific evidence, the Court held that in a given case, when highest limit is stipulated instead of a fixed sum, in absence of evidence of loss, part of it can be held to be reasonable compensation and the remaining by way of penalty. The bench of T.S Thakur and A.K. Goel, JJ further held that the party complaining of breach can certainly be allowed reasonable compensation out of the said amount if not the entire amount. If the entire amount stipulated is genuine pre-estimate of loss, the actual loss need not be proved. Burden to prove that no loss was likely to be suffered is on party committing breach.

In the case where the parties were represented by Kundan Kumar Mishra and Binu Tamta, the respondent awarded a contract to the appellant for constructing a sewerage pumping station. However, the said contract was terminated due to delay in execution of the work resulted in loss for which the respondent was entitled to reasonable compensation. Considering the facts of the case, the Court said that evidence of precise amount of loss may not be possible but in absence of any evidence by the party committing breach that no loss was suffered by the party complaining of breach, the Court has to proceed on guess work as to the quantum of compensation to be allowed in the given circumstances. Since the respondent neither showed the extent of higher amount paid for the work got done nor produced any other specific material but it did not do so, the Court awarded half of the amount claimed as reasonable compensation. [Construction & Design Services v. Delhi Development Authority, , decided on 04.02.2015]

Article referred: http://blog.scconline.com/post/2015/02/06/extent-of-allowing-stipulated-liquidated-damages-by-way-of-penalty-in-absence-of-evidence-of-actual-loss-discussed.aspx

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Court approached in the early stages of arbitration will prevail in all other subsequent proceedings

In National Highway Authority of India v. Hindustan Steelworks Construction Limited, the Hon'ble Delhi High Court opined that once the parties have approached a certain court for relief under Act at earlier stages of disputes then it is same court that, parties must return to for all other subsequent proceedings. Language of Section 42 of Act is categorical and brooks no exception. In fact, the language used has the effect of jurisdiction of all courts since it states that once an application has been made in Part I of the Act then ―that Court alone shall have jurisdiction over arbitral proceedings and all subsequent applications arising out of that agreement and arbitral proceedings shall be made in that Court and in no other Court. Court holds that NHAI in present case cannot take advantage of Section 14 of the Limitation Act, 1963 for explaining inordinate delay in filing present petition under Section 34 of this Act in this Court.

Procedure to be followed on admissibility of additional evidence at appeal stage

In The Corporation of Madras vs M. Parthasarathy & Ors., the trial court had allowed the respondent company to file evidence in the form of photocopies and had dismissed all the four suits filed by the respondents with costs as the evidence were in the form of photocopies and were objected to by the respondents. On appeal the Additional District Judge allowed the respondents to file additional evidence in the form the original documents of the earlier admitted photocopies and based on the same allowed the appeal. In its turn the High Court also dismissed the appeal filed by the appellants who in turn approached the Supreme Court. The Supreme Court decided that the first Appellate Court committed two jurisdictional errors in allowing the appeals.  Referring to earlier judgements of the Supreme Court in Land Acquisition Officer, City Improvement Trust Board vs. H. Narayanaiah & Ors., , Shalimar Chemical Works Ltd. vs. Surendra Oil & Dal Mills (Refineri...