Skip to main content

Builder has to pay compensation if project is delayed

Building projects are often delayed due to disputes between a builder, land owner and developer. Builders try to term these as force majeure, which means due to circumstances beyond their control, to avoid being held liable for deficiency in service. In a recent ruling, the National Commission has held that such disputes cannot be termed force majeure, and a consumer would be entitled to claim a refund along with interest and compensation when the builder is unable to complete the housing project in time. However, a builder can neither unilaterally extend the date of possession nor insist on allotting alternate flat or plot to escape refunding the amount.

Shahin Mulla wanted to purchase a residential unit in "Amar Prem", a housing project in Goa, to be developed by Utopia Projects. The entire consideration of Rs 30 lakh was paid in two instalments of Rs 15 lakh each.

The agreement for construction and sale was executed thereafter on February 24, 2012. It stipulated that possession would be given by September 2013, but the builder would be entitled to a grace period of four months, i.e. till January 2014.

When Mulla visited the site in August 2013, she found that even the foundation had not been laid. She got a legal notice issued to the builder, which was ignored. So she filed a complaint before the Goa State Commission.

The builder contested the complaint, explaining that they had been assigned development rights by RPC Builders and Developers, who had later committed various breaches and were also demanding extra payment for the property. As a result of the dispute, work could not commence. The builder termed the dispute as force majeureand not due to any wilful default. Utopia Projects also pointed out that the complaint was premature as it had been filed prior to January 2014, which was the date of possession inclusive of the grace period.

The state commission observed that the agreement provided that in case of any delay beyond the grace period, the builder would pay the purchaser a monthly compensation at Rs 50 per sq.ft. The defence of force majeure cannot be invoked as the agreement had not been terminated due to inability to perform it.

The state commission concluded that there was deficiency in service and ordered the builder to refund the amount of Rs 30 lakh along with 5% interest from the date of payment of each instalment till the extended date of possession. For the delay, the commission directed payment of a monthly compensation of Rs 50 per sq. ft. from February 1, 2014 till the date of payment. For mental agony, a further amount of Rs 1 lakh was awarded, which would carry 9% interest if not paid within 30 days.

Utopia Projects appealed to the National Commission, contending that the company had formulated a revised schedule, but Mulla was not willing to accept it. In its judgment of April 1, 2015 delivered by M Shreesha for the Bench along with Justice DK Jain and Vinay Kumar, the National Commission held that a consumer is not concerned with the internal disputes between the landowner, developer or contractor. A builder cannot take shelter by wrongly terming internal disputes as force majeure. It ruled that Mulla was well within her rights to demand possession within the stipulated time or else seek a refund along with compensation. Accordingly, the National Commission rejected the builder's appeal, holding that the state commission had rightly allowed Mulla's claim.

Article referred: http://timesofindia.indiatimes.com/city/mumbai/Builder-has-to-pay-compensation-if-project-is-delayed/articleshow/47143531.cms

Comments

Most viewed this month

Michigan House Approves 'Right-to-Work' Bill

Amid raucous protests, the Republican-led Michigan House approved a contentious right-to-work bill on  Dec 11 limiting unions' strength in the state where the (Union for American Auto Workers)  UAW was born. The chamber passed a measure dealing with public-sector workers 58-51 as protesters shouted "shame on you" from the gallery and huge crowds of union backers massed in the state Capitol halls and on the grounds. Backers said a right-to-work law would bring more jobs to Michigan and give workers freedom. Critics said it would drive down wages and benefits. The right-to-work movement has been growing in the country since Wisconsin fought a similar battle with unions over two years ago. Michigan would become the 24th state to enact right-to-work provisions, and passage of the legislation would deal a stunning blow to the power of organized labor in the United States. Wisconsin Republicans in 2011 passed laws severely restricting the power of public s...

Power to re-assess by AO and disclosure of material facts

In AVTEC Limited v. DCIT, the division of the Delhi High Court held that AO is bound to look at the litigation history of the assessee and cannot expect the assessee to inform him.  In the instant case, the Petitioner, engaged in the business of manufacturing and selling of automobiles, power trains and power shift transmissions along with their components, approached the High Court challenging the re-assessment order passed against them. For the year 2006-07, the Petitioner entered into a Business Transfer Agreement with Hindustan Motors Ltd, as per which, the Petitioner took over the business from HML.  While filing income tax return for the said year, the petitioner claimed the expenses incurred in respect of professional and legal charges for the purpose of taking over of the business from HML as capital expenses and claimed depreciation. Article referred: http://www.taxscan.in/assessing-officer-bound-look-litigation-history-assessee-delhi-hc-read-order/8087/

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...