Skip to main content

Builder has to pay compensation if project is delayed

Building projects are often delayed due to disputes between a builder, land owner and developer. Builders try to term these as force majeure, which means due to circumstances beyond their control, to avoid being held liable for deficiency in service. In a recent ruling, the National Commission has held that such disputes cannot be termed force majeure, and a consumer would be entitled to claim a refund along with interest and compensation when the builder is unable to complete the housing project in time. However, a builder can neither unilaterally extend the date of possession nor insist on allotting alternate flat or plot to escape refunding the amount.

Shahin Mulla wanted to purchase a residential unit in "Amar Prem", a housing project in Goa, to be developed by Utopia Projects. The entire consideration of Rs 30 lakh was paid in two instalments of Rs 15 lakh each.

The agreement for construction and sale was executed thereafter on February 24, 2012. It stipulated that possession would be given by September 2013, but the builder would be entitled to a grace period of four months, i.e. till January 2014.

When Mulla visited the site in August 2013, she found that even the foundation had not been laid. She got a legal notice issued to the builder, which was ignored. So she filed a complaint before the Goa State Commission.

The builder contested the complaint, explaining that they had been assigned development rights by RPC Builders and Developers, who had later committed various breaches and were also demanding extra payment for the property. As a result of the dispute, work could not commence. The builder termed the dispute as force majeureand not due to any wilful default. Utopia Projects also pointed out that the complaint was premature as it had been filed prior to January 2014, which was the date of possession inclusive of the grace period.

The state commission observed that the agreement provided that in case of any delay beyond the grace period, the builder would pay the purchaser a monthly compensation at Rs 50 per sq.ft. The defence of force majeure cannot be invoked as the agreement had not been terminated due to inability to perform it.

The state commission concluded that there was deficiency in service and ordered the builder to refund the amount of Rs 30 lakh along with 5% interest from the date of payment of each instalment till the extended date of possession. For the delay, the commission directed payment of a monthly compensation of Rs 50 per sq. ft. from February 1, 2014 till the date of payment. For mental agony, a further amount of Rs 1 lakh was awarded, which would carry 9% interest if not paid within 30 days.

Utopia Projects appealed to the National Commission, contending that the company had formulated a revised schedule, but Mulla was not willing to accept it. In its judgment of April 1, 2015 delivered by M Shreesha for the Bench along with Justice DK Jain and Vinay Kumar, the National Commission held that a consumer is not concerned with the internal disputes between the landowner, developer or contractor. A builder cannot take shelter by wrongly terming internal disputes as force majeure. It ruled that Mulla was well within her rights to demand possession within the stipulated time or else seek a refund along with compensation. Accordingly, the National Commission rejected the builder's appeal, holding that the state commission had rightly allowed Mulla's claim.

Article referred: http://timesofindia.indiatimes.com/city/mumbai/Builder-has-to-pay-compensation-if-project-is-delayed/articleshow/47143531.cms

Comments

Most viewed this month

Merits and the terms of contract are irrelevant for invoking of the bank guarantees

In Sabarkantha Annuity Pvt. Ltd. Vs. NHAI and Ors, the Petitioner filed before the Delhi High Court  petition under Section 9 of the Arbitration and Conciliation (Amendment) Act, 2015 with a prayer that, Respondents be restrained from acting upon the letter dated 15th September, 2017 or from invoking the Bid securities of the Petitioner to the tune of Rs. 10.93 Crores and also restraining the banks from honouring the invocation of said bank guarantees on behalf of Respondent No. 1 acting in terms of letter dated 3rd November, 2007. Petitioner has relied upon Clauses Nos. 9.1.1, 9.1.2 and 4.3 of the agreement dated 28th April, 2017 entered into between the parties to say the claim for damages since is not a claim for a sum presently due and payable and the respondent would be entitled to damages only on proof of loss, per Clause 4.3 of the agreement and hence is not entitle to the entire sum of bid security.  The Court found that Clause No. 9.1.2 speaks of an exclusiv...

Right of pre-emption under West Bengal Land Reform Act

In Rabindra Nath Kundu & Anr vs Sudhir Hira, Bijoy Krishna Hira being the owner in the suit plot, gifted to Santosh Kumar Hira demarcated 11 decimals of land vide deed of gift dated 27.4.2004 and the latter sold 9 decimals out of 11 decimals of land to Sudhir Hira the preemptor/opposite party no. 1 and well demarcated 1.65 decimals of land in the said plot along with several other plots were sold, transferred and conveyed to the preemptees/petitioners herein by a registered deed of sale dated 10.8.2010, the subject matter of preemption. It is argued on behalf of the preemptees that  the present opposite party no. 1/preemptor Sudhir Hira has no relationship of co-sharership with Santosh Kumar Hira opposite party no. 2 as the demarcated portion of land has been purchased. It is settled principle of law that partial preemption is not permissible and this was what the view adopted by this Hon'ble High Court is Surendra Vs. Abhimannu reported in (1980) 1 Cal LJ 135 whe...

CBI has no jurisdiction to probe affairs of medical college:HC

The Madras High Court has quashed charges against administrators of a medical college and dismissed CBI's petitions opposing discharge of officials of two other medical colleges, saying the investigation agency, or any other external agency for that matter, has no jurisdiction to probe the affairs of a medical college. Quashing the charges against the administrators of a medical college and dismissing CBI's petitions opposing the discharge of officials of two other medical colleges, Justice Aruna Jagadeesan said "contravention of rules and regulations may be an offence against the statute but is not a crime. There is no room or jurisdiction for any external agency to investigate the affairs of any medical institution coming within the purview of the Medical Council of India." In identical set of orders, all delivered on August 6, Justice Jagadeesan said "the shortfall in faculties and submissions of fake/forged documents would only disentitle the institution...