Skip to main content

Builder has to pay compensation if project is delayed

Building projects are often delayed due to disputes between a builder, land owner and developer. Builders try to term these as force majeure, which means due to circumstances beyond their control, to avoid being held liable for deficiency in service. In a recent ruling, the National Commission has held that such disputes cannot be termed force majeure, and a consumer would be entitled to claim a refund along with interest and compensation when the builder is unable to complete the housing project in time. However, a builder can neither unilaterally extend the date of possession nor insist on allotting alternate flat or plot to escape refunding the amount.

Shahin Mulla wanted to purchase a residential unit in "Amar Prem", a housing project in Goa, to be developed by Utopia Projects. The entire consideration of Rs 30 lakh was paid in two instalments of Rs 15 lakh each.

The agreement for construction and sale was executed thereafter on February 24, 2012. It stipulated that possession would be given by September 2013, but the builder would be entitled to a grace period of four months, i.e. till January 2014.

When Mulla visited the site in August 2013, she found that even the foundation had not been laid. She got a legal notice issued to the builder, which was ignored. So she filed a complaint before the Goa State Commission.

The builder contested the complaint, explaining that they had been assigned development rights by RPC Builders and Developers, who had later committed various breaches and were also demanding extra payment for the property. As a result of the dispute, work could not commence. The builder termed the dispute as force majeureand not due to any wilful default. Utopia Projects also pointed out that the complaint was premature as it had been filed prior to January 2014, which was the date of possession inclusive of the grace period.

The state commission observed that the agreement provided that in case of any delay beyond the grace period, the builder would pay the purchaser a monthly compensation at Rs 50 per sq.ft. The defence of force majeure cannot be invoked as the agreement had not been terminated due to inability to perform it.

The state commission concluded that there was deficiency in service and ordered the builder to refund the amount of Rs 30 lakh along with 5% interest from the date of payment of each instalment till the extended date of possession. For the delay, the commission directed payment of a monthly compensation of Rs 50 per sq. ft. from February 1, 2014 till the date of payment. For mental agony, a further amount of Rs 1 lakh was awarded, which would carry 9% interest if not paid within 30 days.

Utopia Projects appealed to the National Commission, contending that the company had formulated a revised schedule, but Mulla was not willing to accept it. In its judgment of April 1, 2015 delivered by M Shreesha for the Bench along with Justice DK Jain and Vinay Kumar, the National Commission held that a consumer is not concerned with the internal disputes between the landowner, developer or contractor. A builder cannot take shelter by wrongly terming internal disputes as force majeure. It ruled that Mulla was well within her rights to demand possession within the stipulated time or else seek a refund along with compensation. Accordingly, the National Commission rejected the builder's appeal, holding that the state commission had rightly allowed Mulla's claim.

Article referred: http://timesofindia.indiatimes.com/city/mumbai/Builder-has-to-pay-compensation-if-project-is-delayed/articleshow/47143531.cms

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

When debt is bona fide disputed and the defence is a substantial one, the court will not wind up the company

In SHITAL FIBERS LTD.  vs  INDIAN ACRYLICS LIMITED, as per the respondent, appellant had made a payment of Rs.61,83,218/­. However, there was an outstanding balance of Rs.8,92,723/­ as on 28.7.2008. Since despite repeated requests, balance amount was not paid, the respondent issued a statutory notice to the appellant. The same was duly responded to. As the payment was not made despite notice being duly served on the appellant, the respondent filed the aforesaid Company Petition seeking winding up of the present appellant for its inability to pay admitted debts. The learned Company Judge vide order dated 28.9.2015 admitted the Company Petition. However, while doing so, the learned Company Judge observed, that since the appellant was an on­going concern, an opportunity should be granted to it to settle the accounts with the respondent by 31.12.2015. Only in case of failure of the settlement, the citation was directed to be published. On appeal, the Division Bench of the High Cou...

Abusing in-laws a ground for divorce: SC

Abusing in-laws and not allowing them to reside in the matrimonial home by a woman amounts to cruelty to her spouse, ground enough for grant of divorce, the Supreme Court has ruled while allowing an NRI's plea for legal separation from his wife. A bench of Justices Vikaramajit Sen and A M Sapre said such incidents could not be termed as "wear and tear" of family life as held by Madras High Court which had said that a couple must be prepared to face such situations in matrimonial relationship. The NRI had filed a divorce petition alleging that his wife was abusive to his family members and did not allow his parents and siblings to stay in his house when they visited the US. Referring to an incident, the husband told the court that his wife had once locked him and his sister out of the house and abused them saying they belonged to a 'prostitute family'. She refused to allow her sister-in-law to enter the house and even lodged a police complaint against her hu...