Real estate firm directed to pay Rs 4.77 cr for 'huge delay'

A real estate firm has been directed by the apex consumer commission to pay Rs 4.77 crore to seven consumers for "huge delay" in handing over apartments to them noting that the builder had attempted to make profit at the cost of others.

The National Consumer Disputes Redressal Commission bench presided by Justice J M Malik noted that the apartments booked nine years ago in Greater Noida were yet to be delivered by Unitech Reliable Projects Pvt Ltd and asked it to pay Rs 4,77,58,658 with 18 per cent interest to the seven consumers.

"There is a magic in that little word 'home'. It is a mystic circle and surrounds comforts and virtues, never known beyond its hollowed limits. However, customers are exasperated by senseless delay made by the Builder of a colony," the commission said.

"It must be borne in mind that there is a huge delay in handing over possession of the premises in dispute, i.E., about 9 years. The Opposite Party (builder) has made an attempt to feather its own nest, i.E., to make profits for itself, at the cost of others' expenses. The Opposite Party has utilised the amount for its own purposes," it said.

The commission also directed the firm to pay Rs one lakh each to the complainants for harassment and mental agony.

According to the complainants, in 2006-07, the real-estate firm had advertised for availability of flats in their projects 'Unitech Verve' in Sector Pi-II at Greater Noida in Uttar Pradesh which was scheduled to be delivered within 36 months of signing of allotment letter.

The seven complainants said that they had applied for flats, either individually or jointly, and had paid the money demanded by the builder.

However, after the project got delayed, they filed complaint before the commission in October 2012.

The firm submitted before the commission that it was unable to hand over the possession of apartments to them.

It, however, submitted that it was ready to pay 10 per cent interest to the consumers as per the agreement entered into between the parties.

Article referred: http://www.business-standard.com/article/pti-stories/real-estate-firm-directed-to-pay-rs-4-77-cr-for-huge-delay-115050800990_1.html

Comments

Most viewed this month

Appellate authorities under Special Statutes cannot be asked to condone delay

Madras High Court in R.Gowrishankar vs. The Commissioner of Service Tax has held that Appellate authorities cannot be asked to condone the delay, beyond the extended period of limitation A Division Bench comprising of Justices S. Manikumar and D. Krishnakumar, made this observation while considering an appeal filed against Single Bench order declining to set aside the order made in the condone delay petition filed by the petitioner to condone 223 days in filing the appeal before the Commissioner of Service Tax (Appeals). Article referred: http://www.livelaw.in/appellate-authorities-special-statutes-cannot-asked-condone-delay-beyond-extended-period-limitation-madras-hc/

'Seize assets to pay damages to accident victim'

Her story might be an inspiration for the physically challenged but justice has remained elusive for her. In 2008, a bus accident left research engineer S Thenmozhi, 30, paraplegic. In April 2013, the motor accident claims tribunal directed the Tamil Nadu State Transport Corporation (TNSTC) to provide her a compensation of 57.9 lakh. However, TNSTC refused to budge and on Tuesday a city court ordered attaching of movable assets of the transport corporation. Thenmozhi was employed in C-DOT, a telecom technology development centre in Bangalore. On July 21, 2008, she was coming to Chennai in a private bus. Around 2am, the bus had a flat tyre and the driver parked it on the left side of the road near Pallikonda in Vellore district on the Bangalore-Chennai highway. While the tyre was being changed, a TNSTC bus of Dharmapuri division hit the stationary bus. The rear part of the bus was smashed and passengers were injured. Thenmozhi who had a seat at the back of the bus suffered...

Mumbai ITAT rules income of offshore discretionary trust is subject to tax in India

The Mumbai Income Tax Appellate Tribunal (ITAT) has recently determined the following issue in the affirmative in the case of Manoj Dhupelia: Should the income of an offshore discretionary trust be subject to tax in India, if no distributions have been made to beneficiaries in India? The question arose from appeals filed by individual beneficiaries in relation to a Lichtenstein-based trust, the Ambrunova Trust and Merlyn Management SA (the Trust) with the ITAT. It is important to note that the individuals in this case were amongst those first identified by the Government of India (GOI) as holding undeclared bank accounts in Lichtenstein. The ITAT ruling raises the following issues: Taxation of Trust Corpus: ITAT classified the corpus of the trust as "undisclosed income" and declared it taxable in the hands of the beneficiaries. Taxation of Undistributed Income: ITAT refused to draw a distinction between the corpus and undistributed income from the trust and declared i...