The law says that a contract to do an act, which turns out to be impossible of performance after the agreement, becomes void and the person who suffers must be compensated. If environment restrictions not contemplated in the contract frustrate a project and it becomes impossible or impracticable to implement it, the contractor deserves compensation, according to the Supreme Court. The contractor who could not undertake a housing project because of environment curbs not contemplated by the government at the time of signing the agreement was compensated in the judgment,
Partition proceedings are vitiated even if single co-sharer is not made party or is not served in accordance with law
Cause Title : Bhagwant Singh vs Financial Commissioner (Appeals) Punjab, Chandigarh, CWP-2132-2018 (O&M), High Court Of Punjab & Haryana At Chandigarh Date of Judgment/Order : 31.08.2022 Corum : Hon’ble Mr. Justice Sudhir Mittal Background A large parcel of land was owned by the Nagar Panchayat. Thereafter, some of the co-sharers sold their shares to third parties including the petitioners herein. On 22.11.1995, respondents No.3 to 5 filed an application for partition of the land. The petitioners were not impleaded as parties. On completion of proceedings, sanad was issued on 28.08.1996. Vide two separate sale deeds dated 28.05.2008 respondents No.3 and 5 sold some portion in favour of respondent No.6 and 7. These respondents sought implementation of the sanad resulting in issuance of warrants of possession dated 05.06.2008. Allegedly, it was then that the petitioners realized that joint land had been partitioned and that proceedings h...
Comments
Post a Comment