Skip to main content

Delay caused in an act required to be done by Government authority

In Cheema Spintex Ltd. V. Commissioner of Customs (ICD) TKD, New Delhi, Customs, Excise and Service Tax Appellate Tribunal held that delay caused in an act required to be done by Government authority cannot be adopted as ground for penalizing innocent Appellant.

In instant case, Appellant was a 100% EOU engaged in manufacture and export of cotton yarn. Appellant sought permission to opt out of EOU scheme. Development Commissioner gave approval to exit from EOU scheme on payment of duty on capital goods under prevalent EPCG scheme. Said directions of Development Commissioner were complied with by Appellant including calculation of duty liability. Duty so calculated was finally paid by Appellant. Appellant applied for 'No Dues Certificate' which was given by Deputy Commissioner, on 3rd December, 2007. After 'No Dues Certificate', final de-bonding order was issued by Development Commissioner. Thereafter, Appellant had effected 70 exports under 70 free shipping bills. As per Appellant, they were made to file free shipping bills in respect of exports made after 26th September, 2007, even though, they had fully paid requisite duty, as final de-bonding order was yet to be passed.

Appellant applied to Revenue for conversion of 70 free shipping bills into draw back shipping bills in respect of export of cotton yarn made during intervening period from 26th September, 2007 to 9th January, 2008. Adjudicating authority vide impugned order addressed issue of conversion of free shipping bills to draw back shipping bills and concluded that such conversion was possible. However, he allowed conversion of only 31 shipping bills out of total 70 shipping bills which were filed during period between issuance of 'No Dues Certificate' and issuance of de-bonding order. In respect of shipping bills filed prior to issuance of 'No Dues Certificate', he rejected such conversion on ground that inasmuch 'No Dues Certificate' was not issued by Revenue, such conversion request cannot be accepted.

The Tribunal said that Appellant completed all formalities and discharged their duty obligation on 26th September, 2007 and applied to Revenue for issuance of 'No Dues Certificate'. Said certificate could have been issued by Revenue within a period of one week, two weeks or so, in which case the benefit would have been granted to Appellant even earlier. There is no answer as to why issuance of said certificate took more than two months. Issuance of certificate is not in hands of Appellants and delay taken by Revenue for issuance of such certificate cannot act prejudice to Appellants interest. Delay caused in an act required to be done by Government authority cannot be adopted as a ground for penalizing an innocent Appellant. As such, date of issuance of 'No Dues Certificate' by Revenue cannot be adopted as a relevant date so as to decide Appellant's right to conversion of shipping bills. 

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Amendment of plaint under Order VI Rule 17 of the CPC explained

Cause Title :  Ganesh Prasad vs Rajeshwar Prasad, SLP (C) NO. 28377 OF 2018, Supreme Court Of India Date of Judgment/Order : 14/3/2023 Corum : J. B. Pardiwala, J. Citied:  Revajeetu Builders and Developers v. Narayanaswamy & Sons and Others reported in (2009) 10 SCC 84 North Eastern Railway Administration, Gorakhpur v. Bhagwan Das reported in (2008) 8 SCC 511 P.A. Jayalakshmi v. H. Saradha and Others reported in (2009) 14 SCC 525 B.K. Narayana Pillai v. Parameswaran Pillai and Another reported in (2000) 1 SCC 712 A.K. Gupta and Sons Ltd. v. Damodar Valley Corporation reported in AIR 1967 SC 96 Life Insurance Corporation of India v. Sanjeev Builders Private Limited and Another, Civil Appeal No. 5909 of 2022 dated 01.09.2022 Firm Sriniwas Ram Kumar v. Mahabir Prasad and Others reported in AIR 1951 SC 177 G. Nagamma and Another v. Siromanamma and Another reported in (1996) 2 SCC 25 Praful Manohar Rele v. Krishnabai Narayan Ghosalkar and Others reported in (2014...

Owner of vehicle is not expected to verify the genuineness of the driving license before appointing a driver

Cause Title : Rishi Pal Singh Versus New India Assurance Co. Ltd & Ors., Civil Appeal No. 4919 Of 2022, The Supreme Court Of India Date of Judgment/Order : July 26, 2022 Corum : Hemant Gupta; J., Vikram Nath; J. Background the truck owned by the appellant met with an accident. The owner deposed before the court that before employing the driver, he had taken his driving test and that he was driving the vehicle satisfactorily and  that the driver was employed with him for 3 years before the date of the accident. He produced his driving license. This was reaffirmed by the driver who deposed that the driving license was obtained from the driver and it was issued from Nagaland, but no such license was produced on record. Both the Motor Accident Claims Tribunal and the High Court have held that the owner has alleged that the driver had a driving license from Nagaland but the same was not produced and therefore, the Insurance Company is entitled to recover the awarded amount...