Skip to main content

The period of delay is to be counted from the knowledge of the deficiency

In Vinod Kumar Kataria Vs. Arufa,  first appeal has been filed by the Appellant against the order passed by the State Commission. Appellant/complainant had purchased the first floor of the property from the opposite party and sale deed was executed in his favour. The possession of the flat in question was handed over to the complainant in October 2012. It was alleged that, after shifting in the aforesaid premises, the complainant realized that, the OP had used inferior quality material in the construction of the flat and noticed major defects. Based on this fact, the complainant filed complaint before the State Commission for refund of the total amount of purchase price amounting to Rs. 25,00,000/- alongwith Rs. 1,50,000/- as expense of sale deed. The State Commission, however, dismissed the complaint at the admission stage on the ground of limitation and on the ground that other occupants have filed a civil suit for illegal construction and the complainant may also join the same.

From the facts of the case, it is clear that sale deed was executed on 22nd August, 2012 and the possession was handed over in October, 2012. The complaint has been filed on 14th June, 2016. The State Commission has relied upon the judgment of this Commission in Dr. Gopal and Another Vs. Deorao Ganpat Kaore and others, wherein, it has been held that, the period of limitation in respect of patent defects will commence from a date later on the date on which the said patent defects comes to the notice of the complainant. No doubt, a builder is under an obligation to rectify the defects, if any, found in the house constructed by him, but if he fails to do so, the complainant is required to approach a consumer forum within two years from the date on which the said defect is noticed by him for the first time. In case he was prevented by sufficient cause from filing a complaint within the prescribed period of limitation, he must file an application seeking condonation of delay in filing the complaint.

In the present case also, the Appellant has not produced any acknowledgment by the builder that, he admits the defects and that he promised to rectify the same within a particular period. Thus, from the above observation of this Commission, it is clear that the cause of action could not be treated as continuing one. The period of delay is to be counted from the knowledge of the deficiency. In fact, the cause of action has arisen on the date when the possession was taken by the appellant/complainant and it cannot be treated as extended by way of any correspondence between the parties.

The National Commission dismissed the appeal holding that, the complaint was highly time barred and no application for condonation of delay was moved before the State Commission, therefore, the State Commission was totally justified in dismissing the complaint on the ground of limitation. Moreover, the State Commission has also noted that, a civil case has been filed by the other occupants for the alleged illegal construction in the parking space by the opposite party and the complainant has been given liberty to join the same. If a matter is already pending adjudication in a civil Court, the same cannot be considered by the consumer forum simultaneously. Hence, this part of the order of the State Commission is also justified.

Comments

Most viewed this month

Merits and the terms of contract are irrelevant for invoking of the bank guarantees

In Sabarkantha Annuity Pvt. Ltd. Vs. NHAI and Ors, the Petitioner filed before the Delhi High Court  petition under Section 9 of the Arbitration and Conciliation (Amendment) Act, 2015 with a prayer that, Respondents be restrained from acting upon the letter dated 15th September, 2017 or from invoking the Bid securities of the Petitioner to the tune of Rs. 10.93 Crores and also restraining the banks from honouring the invocation of said bank guarantees on behalf of Respondent No. 1 acting in terms of letter dated 3rd November, 2007. Petitioner has relied upon Clauses Nos. 9.1.1, 9.1.2 and 4.3 of the agreement dated 28th April, 2017 entered into between the parties to say the claim for damages since is not a claim for a sum presently due and payable and the respondent would be entitled to damages only on proof of loss, per Clause 4.3 of the agreement and hence is not entitle to the entire sum of bid security.  The Court found that Clause No. 9.1.2 speaks of an exclusiv...

Right of pre-emption under West Bengal Land Reform Act

In Rabindra Nath Kundu & Anr vs Sudhir Hira, Bijoy Krishna Hira being the owner in the suit plot, gifted to Santosh Kumar Hira demarcated 11 decimals of land vide deed of gift dated 27.4.2004 and the latter sold 9 decimals out of 11 decimals of land to Sudhir Hira the preemptor/opposite party no. 1 and well demarcated 1.65 decimals of land in the said plot along with several other plots were sold, transferred and conveyed to the preemptees/petitioners herein by a registered deed of sale dated 10.8.2010, the subject matter of preemption. It is argued on behalf of the preemptees that  the present opposite party no. 1/preemptor Sudhir Hira has no relationship of co-sharership with Santosh Kumar Hira opposite party no. 2 as the demarcated portion of land has been purchased. It is settled principle of law that partial preemption is not permissible and this was what the view adopted by this Hon'ble High Court is Surendra Vs. Abhimannu reported in (1980) 1 Cal LJ 135 whe...

CBI has no jurisdiction to probe affairs of medical college:HC

The Madras High Court has quashed charges against administrators of a medical college and dismissed CBI's petitions opposing discharge of officials of two other medical colleges, saying the investigation agency, or any other external agency for that matter, has no jurisdiction to probe the affairs of a medical college. Quashing the charges against the administrators of a medical college and dismissing CBI's petitions opposing the discharge of officials of two other medical colleges, Justice Aruna Jagadeesan said "contravention of rules and regulations may be an offence against the statute but is not a crime. There is no room or jurisdiction for any external agency to investigate the affairs of any medical institution coming within the purview of the Medical Council of India." In identical set of orders, all delivered on August 6, Justice Jagadeesan said "the shortfall in faculties and submissions of fake/forged documents would only disentitle the institution...