Skip to main content

Unilateral Addition To Contract By Arbitral Tribunal Violates Most Basic Notions Of Justice

In CIVIL APPEAL NO. 4779 OF 2019, Ssangyong Engineering & Construction Co. Ltd. vs National Highways Authority of India (NHAI), the matter arose out of a 2005 work contract between the National Highway Authority of India(NHAI) and Ssangyong Engineering and Construction Company, a Korean company. The contract had a price adjustment formula, which applied the Wholesale Price Index published by Union Government based on the year 1993-94. From 2010 onwards, the Union Ministry started publishing WPI based on 2004-05. The contractor raised the bills accordingly. In 2013, the NHAI issued a circular adopting a new formula applying a "linking factor" based on 2009-10 to the old formula.

The contractor opposed the application of 2013 circular as a unilateral modification of the formula . The dispute was referred to arbitration.

The arbitral tribunal by a 2:1 majority upheld the application of 2013 circular. While doing so, the majority award applied certain government guidelines of the Ministry of Commerce and Industry, which stated that the establishment of a linking factor to connect the Old Series with the New Series is necessary. The majority award further made it clear that these guidelines are available on the official website, though they were not on record in the proceedings.

The dissenting arbitrator expressly stated that neither the Circular nor the guidelines could be applied as they were de hors the contract between the parties.

The challenge made to the award under Section 34 before the Delhi High Court was not successful and the matter reached the Supreme Court at the instance of the Korean contractor.

Referring to BCCI v Kochi Cricket Club, the Supreme Court held that observed that where an arbitral tribunal has rendered an award which decides matters either beyond the scope of the arbitration agreement or beyond the disputes referred to the arbitral tribunal, the arbitral award could be said to have dealt with decisions on matters beyond the scope of submission to arbitration. The bench further added the Section 34(2)(a)(iv) has to be construed narrowly and that it was not possible to say that the misinterpretation of contract by the tribunal would mean that it had gone beyond the scope of submission to arbitration "if otherwise the aforesaid misinterpretation (which would include going beyond the terms of the contract), could be said to have been fairly comprehended as "disputes" within the arbitration agreement.

Article referred: https://www.livelaw.in/top-stories/sec34-arbitration-act-unilateral-addition-to-contract-by-arbitral-tribunal-violates-most-basic-notions-of-justice-sc-144900

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Court approached in the early stages of arbitration will prevail in all other subsequent proceedings

In National Highway Authority of India v. Hindustan Steelworks Construction Limited, the Hon'ble Delhi High Court opined that once the parties have approached a certain court for relief under Act at earlier stages of disputes then it is same court that, parties must return to for all other subsequent proceedings. Language of Section 42 of Act is categorical and brooks no exception. In fact, the language used has the effect of jurisdiction of all courts since it states that once an application has been made in Part I of the Act then ―that Court alone shall have jurisdiction over arbitral proceedings and all subsequent applications arising out of that agreement and arbitral proceedings shall be made in that Court and in no other Court. Court holds that NHAI in present case cannot take advantage of Section 14 of the Limitation Act, 1963 for explaining inordinate delay in filing present petition under Section 34 of this Act in this Court.

No Rebate For Stamp Duty Paid In Another State - Bombay HC

A three judge bench of the Hon'ble Bombay High Court (Bombay HC) in a recent judgment in the matter of Chief Controlling Revenue Authority, Maharashtra State, Pune and Superintendent of Stamp (Headquarters), Mumbai v Reliance Industries Limited, Mumbai and Reliance Petroleum Limited, Gujarat1 has held that orders in case of a scheme of arrangement under Section 391 to 394 of the Companies Act, 1956 (Act) involving different High Courts in multiple states, are separate instruments in themselves. Accordingly, stamp duty would be payable on all the orders (and consequently, all the states) without the benefit of remission, rebate or set-off.