Unilateral Addition To Contract By Arbitral Tribunal Violates Most Basic Notions Of Justice

In CIVIL APPEAL NO. 4779 OF 2019, Ssangyong Engineering & Construction Co. Ltd. vs National Highways Authority of India (NHAI), the matter arose out of a 2005 work contract between the National Highway Authority of India(NHAI) and Ssangyong Engineering and Construction Company, a Korean company. The contract had a price adjustment formula, which applied the Wholesale Price Index published by Union Government based on the year 1993-94. From 2010 onwards, the Union Ministry started publishing WPI based on 2004-05. The contractor raised the bills accordingly. In 2013, the NHAI issued a circular adopting a new formula applying a "linking factor" based on 2009-10 to the old formula.

The contractor opposed the application of 2013 circular as a unilateral modification of the formula . The dispute was referred to arbitration.

The arbitral tribunal by a 2:1 majority upheld the application of 2013 circular. While doing so, the majority award applied certain government guidelines of the Ministry of Commerce and Industry, which stated that the establishment of a linking factor to connect the Old Series with the New Series is necessary. The majority award further made it clear that these guidelines are available on the official website, though they were not on record in the proceedings.

The dissenting arbitrator expressly stated that neither the Circular nor the guidelines could be applied as they were de hors the contract between the parties.

The challenge made to the award under Section 34 before the Delhi High Court was not successful and the matter reached the Supreme Court at the instance of the Korean contractor.

Referring to BCCI v Kochi Cricket Club, the Supreme Court held that observed that where an arbitral tribunal has rendered an award which decides matters either beyond the scope of the arbitration agreement or beyond the disputes referred to the arbitral tribunal, the arbitral award could be said to have dealt with decisions on matters beyond the scope of submission to arbitration. The bench further added the Section 34(2)(a)(iv) has to be construed narrowly and that it was not possible to say that the misinterpretation of contract by the tribunal would mean that it had gone beyond the scope of submission to arbitration "if otherwise the aforesaid misinterpretation (which would include going beyond the terms of the contract), could be said to have been fairly comprehended as "disputes" within the arbitration agreement.

Article referred: https://www.livelaw.in/top-stories/sec34-arbitration-act-unilateral-addition-to-contract-by-arbitral-tribunal-violates-most-basic-notions-of-justice-sc-144900

Comments

Most viewed this month

Amendment of plaint under Order VI Rule 17 of the CPC explained

Cause Title :  Ganesh Prasad vs Rajeshwar Prasad, SLP (C) NO. 28377 OF 2018, Supreme Court Of India Date of Judgment/Order : 14/3/2023 Corum : J. B. Pardiwala, J. Citied:  Revajeetu Builders and Developers v. Narayanaswamy & Sons and Others reported in (2009) 10 SCC 84 North Eastern Railway Administration, Gorakhpur v. Bhagwan Das reported in (2008) 8 SCC 511 P.A. Jayalakshmi v. H. Saradha and Others reported in (2009) 14 SCC 525 B.K. Narayana Pillai v. Parameswaran Pillai and Another reported in (2000) 1 SCC 712 A.K. Gupta and Sons Ltd. v. Damodar Valley Corporation reported in AIR 1967 SC 96 Life Insurance Corporation of India v. Sanjeev Builders Private Limited and Another, Civil Appeal No. 5909 of 2022 dated 01.09.2022 Firm Sriniwas Ram Kumar v. Mahabir Prasad and Others reported in AIR 1951 SC 177 G. Nagamma and Another v. Siromanamma and Another reported in (1996) 2 SCC 25 Praful Manohar Rele v. Krishnabai Narayan Ghosalkar and Others reported in (2014...

Even An Unregistered Partnership Firm Can Maintain ‘Cheque Bounce’ Complaint

In M/s Uttam Traders Ranghri vs. Tule Ram alias Tula Ram, an appeal was filed before the Himachal Pradesh High Court solely on the ground that one of the partners of the complainant-firm which is an unregistered partnership concern, had failed to prove that he was one of the partners of the complainant-firm and duly authorised by it to file the complaint and acquitted the respondent. The High Court decided that two questions arise for consideration in this matter :- 1) Whether acquittal by the magistrate solely on the ground that the managing partner of the appellant having failed to establish that he was one of the partners of the complainant-firm and duly authorised by it to file the complaint was correct 2) Whether a partner of an unregistered partnership firm can maintain a complaint under Section 138 of the Negotiable Instruments Act. For the first issue, the High Court referred to M/s Haryana State Co.Op., Supply and Marketing Federation Ltd. vs. M/s Jayam Text...

Valuation Report of Jewellery once made is effective for Four Assessment Years

The division Bench of the Delhi High Court in Pr.Commissioner of Wealth Tax vs. Raghu Hari Dalmia held that a valuation report made by a registered valuer once adopted shall be in effect for four assessment years unless an event has occurred whereby the value is increased or decreased. The High Court made it clear that the event of “search” under Section 132 of the Income Tax Act, 1961 cannot compel the assessee to undertake a fresh valuation.