Skip to main content

Developer Liable To Provide Amenities As Well

In Wg. Cdr. Arifur Rahman Khan vs DLF Southern Homes Pvt Ltd., appeal was filed against the order of dismissal by the National Consumer Disputes Redressal Commission on a consumer complaint filed by 339 flat buyers, accepting the defence of DLF Southern Homes Pvt. Ltd. and Annabel Builders and Developers Pvt. Ltd. that there was no deficiency of service on their part in complying with their contractual obligations and, that despite a delay in handing over the possession of the residential flats, the purchasers were not entitled to compensation in excess of what was stipulated in the Apartment Buyers agreement.

The primary grounds on which compensation have been sought before the NCDRC were:

(i) Delay in handing over possession of the flats;

(ii) Reimbursement of taxes and interest charged to the flat purchasers under clause 1.10 of the ABA;

(iii) Deficiency in providing amenities;

(iv) Levy of electricity charges by the developer; and

(v) Failure to construct the club house

The NCDRC divided the group of 339 flat buyers into six groups based on whether or not they had taken possession, executed deeds of conveyance, settled the dispute or sold the flats before or during the pendency of the complaint or their applications for impleadment.

The NCDRC, in the course of its judgment, observed that delay in the handing over of flats to the flat purchasers was admitted and that the agreements provided compensation at the rate of Rs 5 per square foot of the super area for every month of delay.  Referring to the decision of the Supreme Court in DLF Homes Panchkula Pvt. Ltd. v. D S Dhanda and Ghaziabad Development Authority v. Balbir Singh, the NCDRC observed that the developer had while computing the final demand made an adjustment on account of delayed compensation at the rate stipulated in the ABA. The flat purchasers having been provided credit at the rate agreed by the developers, it was held that no further entitlement existed under the law. In the view of the NCDRC, the flat purchasers had failed to prove that the stipulation contained in the agreement for the payment of compensation at Rs 5 per square foot was unreasonable.

Against this order, the appeal was filed.

Disagreeing with this approach, the Apex Court bench observed that, in the instant case, there has been a gross delay on the part of the developer in completing construction ranging between two and four years. 

As for the failure of the developer in developing and providing amenities promised in the brochure but falling outside the areas directly occupied by the flat owners or the common areas, like school, health centre etc. assured/promised by the developer in the sale brochure, the court held that developer must be held accountable to its representation. Refusing to acceed to the developers arguments that some of the amenities are there in the surrounding areas and that building the said amenities directly inside the complex being built by the developer would not be viable, the court held that a flat purchaser who invests in a flat does so on an assessment of its potential. The amenities which the builder has committed to provide impinge on the quality of life for the families of purchasers and the potential for appreciation in the value of the flat. The representation held out by the developer cannot be dismissed as chaff. True, in a situation such as the present it may be difficult for the court to quantify the exact nature of the compensation that should be provided to the flat buyers. The general appreciation in land values results in an increase in the value of the investment made by the buyers. Difficulties in determining the measure of compensation cannot however dilute the liability to pay. A developer who has breached a clear representation which has been made to the buyers of the amenities which will be provided to them should be held accountable to the process of law. To allow the developer to escape their obligation would put a premium on false assurances and representations made to the flat purchasers. Hence, in factoring in the compensation which should be provided to the flat buyers who are concerned in the present batch of appeals, we would necessarily have to bear this issue in mind. 


Comments

Most viewed this month

Merits and the terms of contract are irrelevant for invoking of the bank guarantees

In Sabarkantha Annuity Pvt. Ltd. Vs. NHAI and Ors, the Petitioner filed before the Delhi High Court  petition under Section 9 of the Arbitration and Conciliation (Amendment) Act, 2015 with a prayer that, Respondents be restrained from acting upon the letter dated 15th September, 2017 or from invoking the Bid securities of the Petitioner to the tune of Rs. 10.93 Crores and also restraining the banks from honouring the invocation of said bank guarantees on behalf of Respondent No. 1 acting in terms of letter dated 3rd November, 2007. Petitioner has relied upon Clauses Nos. 9.1.1, 9.1.2 and 4.3 of the agreement dated 28th April, 2017 entered into between the parties to say the claim for damages since is not a claim for a sum presently due and payable and the respondent would be entitled to damages only on proof of loss, per Clause 4.3 of the agreement and hence is not entitle to the entire sum of bid security.  The Court found that Clause No. 9.1.2 speaks of an exclusiv...

Right of pre-emption under West Bengal Land Reform Act

In Rabindra Nath Kundu & Anr vs Sudhir Hira, Bijoy Krishna Hira being the owner in the suit plot, gifted to Santosh Kumar Hira demarcated 11 decimals of land vide deed of gift dated 27.4.2004 and the latter sold 9 decimals out of 11 decimals of land to Sudhir Hira the preemptor/opposite party no. 1 and well demarcated 1.65 decimals of land in the said plot along with several other plots were sold, transferred and conveyed to the preemptees/petitioners herein by a registered deed of sale dated 10.8.2010, the subject matter of preemption. It is argued on behalf of the preemptees that  the present opposite party no. 1/preemptor Sudhir Hira has no relationship of co-sharership with Santosh Kumar Hira opposite party no. 2 as the demarcated portion of land has been purchased. It is settled principle of law that partial preemption is not permissible and this was what the view adopted by this Hon'ble High Court is Surendra Vs. Abhimannu reported in (1980) 1 Cal LJ 135 whe...

CBI has no jurisdiction to probe affairs of medical college:HC

The Madras High Court has quashed charges against administrators of a medical college and dismissed CBI's petitions opposing discharge of officials of two other medical colleges, saying the investigation agency, or any other external agency for that matter, has no jurisdiction to probe the affairs of a medical college. Quashing the charges against the administrators of a medical college and dismissing CBI's petitions opposing the discharge of officials of two other medical colleges, Justice Aruna Jagadeesan said "contravention of rules and regulations may be an offence against the statute but is not a crime. There is no room or jurisdiction for any external agency to investigate the affairs of any medical institution coming within the purview of the Medical Council of India." In identical set of orders, all delivered on August 6, Justice Jagadeesan said "the shortfall in faculties and submissions of fake/forged documents would only disentitle the institution...