Skip to main content

Depending on the situation, subsequent purchaser of flat can have the same right as the original allottee

In M/s Laureate Buildwell Pvt. Ltd vs Charanjeet Singh, the allotment letter dated 16.10.2012 assured the original allottee that the possession of the flat would be handed over within 36 months i.e. on or before 15.10.2015. The original allotee made payment to the tune of Rs. 1,55,89,329/-, towards the first seven instalments as and when demanded. She sold the flat and an agreement to sell was executed between the parties on 17.02.2016. The original allottee thereafter approached the builder, informing it that the purchaser had stepped into her shoes and would continue with the obligations, and was therefore entitled to possession. Significantly, the builder endorsed and even required the purchaser to execute the letter of undertaking, which he did. With this development, the builder acknowledged that the rights and entitlements of the original allottee relation to the flat were assumed by the purchaser, and signified its obligations, correspondingly to the purchaser, as the consumer. 

In the meanwhile, there was a slowdown in construction, apparently, on account of orders made by NGT which imposed certain restrictions within 10 km radius of the Okhla Bird Sanctuary. It appears that there was no construction of the project for about six months. However, despite this position, the builder continued to demand and received instalments. The purchaser entered the scene in 2016, waited for some time and demanded refund of the entire amount with interest from the dates that deposits were made. After receiving notice, the builder demanded further instalments. It was in this background that the purchaser approached the NCDRC successfully with the claim for refund. The claim for interest was allowed to the extent of 10% on the entire amounts deposited from the respective dates of deposits. 

The principal argument of the builder before the Supreme Court while quoting HUDA v. Raje Ram 2008 (17) SCC 407 and the recent judgment of Supreme Court in Wing Commander Arifur Rahman Khan and Anr. v. DLF Southern Homes Pvt. Ltd. 2020 SCC Online 667 (SC) is that the rights of a purchaser are not the same as an original allottee.

The question then is whether a subsequent purchaser is not entitled to similar treatment as the original allottee, and can be denied relief which otherwise the original allottee would have been entitled to, had she or he continued with the arrangement.

The SC observed that the builder does not deny that upon issuance of the endorsement letter, the purchaser not only stepped into the shoes of the original allottee but also became entitled to receive possession of the flat. There is no denial that the purchaser fulfils the description of the complainant/ consumer and is entitled to move any forum under the Consumer Protection Act for any deficiency in service. 

Referring to a larger five judge bench ruling in Economic Transport Organization v. Charan Spinning Mills (P) Ltd (2010) 4 SCC 114 and Canara Bank v. United India Insurance Co. Ltd. (2020) 3 SCC 455,  the SC held that an individual such as the original allottee, enters into an agreement to purchase the flat in an on-going project where delivery is promised. The terms of the agreement as well as the assurance by the builder are that the flat would be made available within a time- frame. It is commonplace that in a large number of such transactions, allottees are not able to finance the flat but seek advances and funds from banks or financial institutions, to which they mortgage the property. The mortgage pay-outs start initially after an agreed period, commencing in a span of about 15 to 24 months after the agreement. This would mean that in most cases, allottees start repaying the bank or financial institutions with instalments (mostly equated monthly instalments) towards the principal and the interest spread over a period of time, even before the flats are ready. If these facts are taken into consideration, prolongation of the project would involve serious economic repercussions upon such original allottees who are on the one hand compelled to pay instalments and, in addition, quite often -if she or he is in want of a house -also pay monthly rents. Such burdens become almost intolerable. It is at this point that an indefinite wait is impossible and allottees prefer to find purchasers who might step into their shoes. That such purchasers take over the obligations of the original allottee – either to pay the balance instalments or to wait for sometime, would not per se exclude them from the description of a consumer. All that then happens is that the consumer forum or commission – or even courts have to examine the relative equities having regard to the time frame in each case. 

In view of these considerations, this court is of the opinion that the per se bar to the relief of interest on refund, enunciated by the decision in Raje Ram (supra) which was applied in Wg. Commander Arifur Rehman (supra) cannot be considered good law. The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent. However, it cannot be said that a subsequent purchaser who steps into the shoes of an original allottee of a housing project in which the builder has not honoured its commitment to deliver the flat within a stipulated time, cannot expect any – even reasonable time, for the performance of the builders obligation. Such a conclusion would be arbitrary, given that there may be a large number- possibly thousands of flat buyers, waiting for their promised flats or residences; they surely would be entitled to all reliefs under the Act. In such case, a purchaser who no doubt enters the picture later surely belongs to the same class. Further, the purchaser agrees to buy the flat with a reasonable expectation that delivery of possession would be in accordance within the bounds of the delayed timeline that he has knowledge of, at the time of purchase of the flat. Therefore, in the event the purchaser claims refund, on an assessment that he too can (like the original allottee) no longer wait, and face intolerable burdens, the equities would have to be moulded. It would no doubt be fair to assume that the purchaser had knowledge of the delay. However, to attribute knowledge that such delay would continue indefinitely, based on an a priori assumption, would not be justified. 

Comments

Most viewed this month

Michigan House Approves 'Right-to-Work' Bill

Amid raucous protests, the Republican-led Michigan House approved a contentious right-to-work bill on  Dec 11 limiting unions' strength in the state where the (Union for American Auto Workers)  UAW was born. The chamber passed a measure dealing with public-sector workers 58-51 as protesters shouted "shame on you" from the gallery and huge crowds of union backers massed in the state Capitol halls and on the grounds. Backers said a right-to-work law would bring more jobs to Michigan and give workers freedom. Critics said it would drive down wages and benefits. The right-to-work movement has been growing in the country since Wisconsin fought a similar battle with unions over two years ago. Michigan would become the 24th state to enact right-to-work provisions, and passage of the legislation would deal a stunning blow to the power of organized labor in the United States. Wisconsin Republicans in 2011 passed laws severely restricting the power of public s...

Power to re-assess by AO and disclosure of material facts

In AVTEC Limited v. DCIT, the division of the Delhi High Court held that AO is bound to look at the litigation history of the assessee and cannot expect the assessee to inform him.  In the instant case, the Petitioner, engaged in the business of manufacturing and selling of automobiles, power trains and power shift transmissions along with their components, approached the High Court challenging the re-assessment order passed against them. For the year 2006-07, the Petitioner entered into a Business Transfer Agreement with Hindustan Motors Ltd, as per which, the Petitioner took over the business from HML.  While filing income tax return for the said year, the petitioner claimed the expenses incurred in respect of professional and legal charges for the purpose of taking over of the business from HML as capital expenses and claimed depreciation. Article referred: http://www.taxscan.in/assessing-officer-bound-look-litigation-history-assessee-delhi-hc-read-order/8087/

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...