Skip to main content

Even when time is not stipulated in a contract, the time period cannot be completely ignored

Cause Title : Yassh Deep Builders Llp vs Sushil Kumar Singh & Anr., Delhi High Court, 

Date of Judgment/Order : 14/3/2023

Corum : Hon’ble Mr. Justice Chandra Dhari Singh

Citied: Saradamani Kandappan vs S. Rajalakshmi & Ors ; (2011) 12 SCC 18

Background

On 15th May, 2018, the petitioner entered into a Collaboration Agreement with the respondent no. 1 for the development of some land belonging to the respondent at its own costs and expenses. Under the terms of the Collaboration Agreement, the petitioner was, inter alia, obliged to apply for licence/ approvals/ permits/ certification etc. for the development of the property in a timely and orderly manner. The Collaboration Agreement stood terminated by the respondent No.1 by way of a letter dated 29th September, 2021 which apparently was never received by the petitioner. 

It is the petitioner's case that on 14.12.2022 on receipt of a phone call regarding the said property for being put for sale, the petitioner made enquiry on 15.12.2022, when it was confronted with the Second Supplementary Collaboration Agreement which is a forged document. The petitioner argued that it has fulfilled its obligations under the Collaboration Agreement. Even otherwise, the petitioner has always been ready and willing to perform its part under the Collaboration Agreement and has been taking all necessary steps to obtain the required licence. Therefore, the petitioner is before this Court seeking interim protection qua the Collaboration Property submitting to the effect that there is a serious and genuine apprehension that the respondent No.1 and 2 would create third party rights in the Collaboration Property to defeat the rights of the petitioner.

The respondent argued that as per Clause 2.14 of the Second Supplementary Collaboration Agreement dated 17th August 2020, the petitioner was to obtain license of the project to be developed on the Collaboration Property by 15th December 2020, however, the petitioner failed to do so. It is further submitted that the petitioner even failed to obtain the required license for the project for almost 40 months, i.e., till the termination of the Collaboration Agreement. It is also submitted that there were consistent defaults on the part of the petitioner submitting to the effect that after execution of the petitioner failed to pay towards the part payment of the security amount as ITS cheque was dishonoured due to “ Insufficient Funds” .

Judgment

On the issue of specific performance, the court held that is trite law that continuous readiness and willingness on the part of the petitioner is a condition precedent for the grant of relief of Specific Performance. It is the bounden duty of the petitioner to prove its readiness and willingness by way of adducing evidence. The crucial facet has to be determined by considering all the circumstances including availability of funds and mere statements or averment in the present petition of readiness and willingness would not suffice. Under Section 16(c) of the Specific Relief Act, a distinction can be drawn between readiness and willingness to perform the contract. Both ingredients are necessary to be established for the grant of relief of the specific performance.

While readiness means the capacity of the petitioner to perform the contract, willingness relates to the conduct of the petitioner. 

It is not disputed that under the Collaboration Agreement (amended by the First Supplementary Agreement), the petitioner was required to get a licence from DTCP in a timely manner which it failed to get even after 5 years. Though this Court knows that the contract did not stipulate a particular time period within which this licence was to be obtained, it ought to have been obtained within a reasonable time period. Thus, the time period cannot be completely ignored. Also. cheques issued by the petitioner towards the part payment of the security amount were dishonoured due to “ Insufficient Funds” .

Capacity of the petitioner to execute the contract was always in doubt. It is not disputed that the petitioner was unable to make payment towards the earnest money as was initially agreed between the parties, which was one of the crucial factors while executing the First Supplementary Agreement.

Further, the petitioner had only paid an amount of Rs.4.21 Crores as earnest money while the price of the land is about at INR 120 Crores. Having paid an amount insignificant in comparison to the value of the property, the petitioner is not entitled to discretionary equitable relief of specific performance.

Comments

Most viewed this month

Appellate authorities under Special Statutes cannot be asked to condone delay

Madras High Court in R.Gowrishankar vs. The Commissioner of Service Tax has held that Appellate authorities cannot be asked to condone the delay, beyond the extended period of limitation A Division Bench comprising of Justices S. Manikumar and D. Krishnakumar, made this observation while considering an appeal filed against Single Bench order declining to set aside the order made in the condone delay petition filed by the petitioner to condone 223 days in filing the appeal before the Commissioner of Service Tax (Appeals). Article referred: http://www.livelaw.in/appellate-authorities-special-statutes-cannot-asked-condone-delay-beyond-extended-period-limitation-madras-hc/

'Seize assets to pay damages to accident victim'

Her story might be an inspiration for the physically challenged but justice has remained elusive for her. In 2008, a bus accident left research engineer S Thenmozhi, 30, paraplegic. In April 2013, the motor accident claims tribunal directed the Tamil Nadu State Transport Corporation (TNSTC) to provide her a compensation of 57.9 lakh. However, TNSTC refused to budge and on Tuesday a city court ordered attaching of movable assets of the transport corporation. Thenmozhi was employed in C-DOT, a telecom technology development centre in Bangalore. On July 21, 2008, she was coming to Chennai in a private bus. Around 2am, the bus had a flat tyre and the driver parked it on the left side of the road near Pallikonda in Vellore district on the Bangalore-Chennai highway. While the tyre was being changed, a TNSTC bus of Dharmapuri division hit the stationary bus. The rear part of the bus was smashed and passengers were injured. Thenmozhi who had a seat at the back of the bus suffered...

Mumbai ITAT rules income of offshore discretionary trust is subject to tax in India

The Mumbai Income Tax Appellate Tribunal (ITAT) has recently determined the following issue in the affirmative in the case of Manoj Dhupelia: Should the income of an offshore discretionary trust be subject to tax in India, if no distributions have been made to beneficiaries in India? The question arose from appeals filed by individual beneficiaries in relation to a Lichtenstein-based trust, the Ambrunova Trust and Merlyn Management SA (the Trust) with the ITAT. It is important to note that the individuals in this case were amongst those first identified by the Government of India (GOI) as holding undeclared bank accounts in Lichtenstein. The ITAT ruling raises the following issues: Taxation of Trust Corpus: ITAT classified the corpus of the trust as "undisclosed income" and declared it taxable in the hands of the beneficiaries. Taxation of Undistributed Income: ITAT refused to draw a distinction between the corpus and undistributed income from the trust and declared i...