Cause Title : Yassh Deep Builders Llp vs Sushil Kumar Singh & Anr., Delhi High Court,
Date of Judgment/Order : 14/3/2023
Corum : Hon’ble Mr. Justice Chandra Dhari Singh
Citied: Saradamani Kandappan vs S. Rajalakshmi & Ors ; (2011) 12 SCC 18
Background
On 15th May, 2018, the petitioner entered into a Collaboration Agreement with the respondent no. 1 for the development of some land belonging to the respondent at its own costs and expenses. Under the terms of the Collaboration Agreement, the petitioner was, inter alia, obliged to apply for licence/ approvals/ permits/ certification etc. for the development of the property in a timely and orderly manner. The Collaboration Agreement stood terminated by the respondent No.1 by way of a letter dated 29th September, 2021 which apparently was never received by the petitioner.
It is the petitioner's case that on 14.12.2022 on receipt of a phone call regarding the said property for being put for sale, the petitioner made enquiry on 15.12.2022, when it was confronted with the Second Supplementary Collaboration Agreement which is a forged document. The petitioner argued that it has fulfilled its obligations under the Collaboration Agreement. Even otherwise, the petitioner has always been ready and willing to perform its part under the Collaboration Agreement and has been taking all necessary steps to obtain the required licence. Therefore, the petitioner is before this Court seeking interim protection qua the Collaboration Property submitting to the effect that there is a serious and genuine apprehension that the respondent No.1 and 2 would create third party rights in the Collaboration Property to defeat the rights of the petitioner.
The respondent argued that as per Clause 2.14 of the Second Supplementary Collaboration Agreement dated 17th August 2020, the petitioner was to obtain license of the project to be developed on the Collaboration Property by 15th December 2020, however, the petitioner failed to do so. It is further submitted that the petitioner even failed to obtain the required license for the project for almost 40 months, i.e., till the termination of the Collaboration Agreement. It is also submitted that there were consistent defaults on the part of the petitioner submitting to the effect that after execution of the petitioner failed to pay towards the part payment of the security amount as ITS cheque was dishonoured due to “ Insufficient Funds” .
Judgment
Comments
Post a Comment