Skip to main content

Even when time is not stipulated in a contract, the time period cannot be completely ignored

Cause Title : Yassh Deep Builders Llp vs Sushil Kumar Singh & Anr., Delhi High Court, 

Date of Judgment/Order : 14/3/2023

Corum : Hon’ble Mr. Justice Chandra Dhari Singh

Citied: Saradamani Kandappan vs S. Rajalakshmi & Ors ; (2011) 12 SCC 18

Background

On 15th May, 2018, the petitioner entered into a Collaboration Agreement with the respondent no. 1 for the development of some land belonging to the respondent at its own costs and expenses. Under the terms of the Collaboration Agreement, the petitioner was, inter alia, obliged to apply for licence/ approvals/ permits/ certification etc. for the development of the property in a timely and orderly manner. The Collaboration Agreement stood terminated by the respondent No.1 by way of a letter dated 29th September, 2021 which apparently was never received by the petitioner. 

It is the petitioner's case that on 14.12.2022 on receipt of a phone call regarding the said property for being put for sale, the petitioner made enquiry on 15.12.2022, when it was confronted with the Second Supplementary Collaboration Agreement which is a forged document. The petitioner argued that it has fulfilled its obligations under the Collaboration Agreement. Even otherwise, the petitioner has always been ready and willing to perform its part under the Collaboration Agreement and has been taking all necessary steps to obtain the required licence. Therefore, the petitioner is before this Court seeking interim protection qua the Collaboration Property submitting to the effect that there is a serious and genuine apprehension that the respondent No.1 and 2 would create third party rights in the Collaboration Property to defeat the rights of the petitioner.

The respondent argued that as per Clause 2.14 of the Second Supplementary Collaboration Agreement dated 17th August 2020, the petitioner was to obtain license of the project to be developed on the Collaboration Property by 15th December 2020, however, the petitioner failed to do so. It is further submitted that the petitioner even failed to obtain the required license for the project for almost 40 months, i.e., till the termination of the Collaboration Agreement. It is also submitted that there were consistent defaults on the part of the petitioner submitting to the effect that after execution of the petitioner failed to pay towards the part payment of the security amount as ITS cheque was dishonoured due to “ Insufficient Funds” .

Judgment

On the issue of specific performance, the court held that is trite law that continuous readiness and willingness on the part of the petitioner is a condition precedent for the grant of relief of Specific Performance. It is the bounden duty of the petitioner to prove its readiness and willingness by way of adducing evidence. The crucial facet has to be determined by considering all the circumstances including availability of funds and mere statements or averment in the present petition of readiness and willingness would not suffice. Under Section 16(c) of the Specific Relief Act, a distinction can be drawn between readiness and willingness to perform the contract. Both ingredients are necessary to be established for the grant of relief of the specific performance.

While readiness means the capacity of the petitioner to perform the contract, willingness relates to the conduct of the petitioner. 

It is not disputed that under the Collaboration Agreement (amended by the First Supplementary Agreement), the petitioner was required to get a licence from DTCP in a timely manner which it failed to get even after 5 years. Though this Court knows that the contract did not stipulate a particular time period within which this licence was to be obtained, it ought to have been obtained within a reasonable time period. Thus, the time period cannot be completely ignored. Also. cheques issued by the petitioner towards the part payment of the security amount were dishonoured due to “ Insufficient Funds” .

Capacity of the petitioner to execute the contract was always in doubt. It is not disputed that the petitioner was unable to make payment towards the earnest money as was initially agreed between the parties, which was one of the crucial factors while executing the First Supplementary Agreement.

Further, the petitioner had only paid an amount of Rs.4.21 Crores as earnest money while the price of the land is about at INR 120 Crores. Having paid an amount insignificant in comparison to the value of the property, the petitioner is not entitled to discretionary equitable relief of specific performance.

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Amendment of plaint under Order VI Rule 17 of the CPC explained

Cause Title :  Ganesh Prasad vs Rajeshwar Prasad, SLP (C) NO. 28377 OF 2018, Supreme Court Of India Date of Judgment/Order : 14/3/2023 Corum : J. B. Pardiwala, J. Citied:  Revajeetu Builders and Developers v. Narayanaswamy & Sons and Others reported in (2009) 10 SCC 84 North Eastern Railway Administration, Gorakhpur v. Bhagwan Das reported in (2008) 8 SCC 511 P.A. Jayalakshmi v. H. Saradha and Others reported in (2009) 14 SCC 525 B.K. Narayana Pillai v. Parameswaran Pillai and Another reported in (2000) 1 SCC 712 A.K. Gupta and Sons Ltd. v. Damodar Valley Corporation reported in AIR 1967 SC 96 Life Insurance Corporation of India v. Sanjeev Builders Private Limited and Another, Civil Appeal No. 5909 of 2022 dated 01.09.2022 Firm Sriniwas Ram Kumar v. Mahabir Prasad and Others reported in AIR 1951 SC 177 G. Nagamma and Another v. Siromanamma and Another reported in (1996) 2 SCC 25 Praful Manohar Rele v. Krishnabai Narayan Ghosalkar and Others reported in (2014...

Owner of vehicle is not expected to verify the genuineness of the driving license before appointing a driver

Cause Title : Rishi Pal Singh Versus New India Assurance Co. Ltd & Ors., Civil Appeal No. 4919 Of 2022, The Supreme Court Of India Date of Judgment/Order : July 26, 2022 Corum : Hemant Gupta; J., Vikram Nath; J. Background the truck owned by the appellant met with an accident. The owner deposed before the court that before employing the driver, he had taken his driving test and that he was driving the vehicle satisfactorily and  that the driver was employed with him for 3 years before the date of the accident. He produced his driving license. This was reaffirmed by the driver who deposed that the driving license was obtained from the driver and it was issued from Nagaland, but no such license was produced on record. Both the Motor Accident Claims Tribunal and the High Court have held that the owner has alleged that the driver had a driving license from Nagaland but the same was not produced and therefore, the Insurance Company is entitled to recover the awarded amount...