Skip to main content

Reference in a contract to a document containing an arbitration clause must be clear and unambiguous

Cause Title : Kobelco Construction Equipment India Private Limited vs. Lara Mining & Anr., AP 181 of 2023, Calcutta High Court

Date of Judgment/Order : 11.08.2023

Corum : Hon’ble Justice Moushumi Bhattacharya

Citied: 

  1. Duro Felguera, S.A. vs. Gangavaram Port Limited; (2017) 9 SCC 729
  2. Inox Wind Limited vs. Thermocables Limited; (2018) 2 SCC 519
  3. M.R. Engineers and Contractors Private Limited vs. Som Datt Builders Limited; (2009) 7 SCC 696
  4. Sea Trade Maritime Corpn. v. Hellenic Mutual War Risks Assn. (Bermuda) Ltd. No. 2; 2006 EWHC 2530
  5. Chloro Controls India Private Limited v Severn Trent Water Purification Inc. ; (2013) 1 SCC 641
  6. Ameet Lalchand Shah vs Rishabh Enterprises; (2018) 15 SCC 678
  7. Tantia Constructions Limited vs. Mather and Platt Pumps Limited in AP No. 72 of 2023

Background

The Arbitration Petitions have been filed under section 9 of The Arbitration and Conciliation Act, 1996 by the petitioner seeks an injunction on the respondent no 1 from dealing with or disposing of the assets under a Master Facility Agreement dated 19th January, 2020 and a Settlement Agreement dated 17th July, 2021.

The Petitioner submitted that the respondent no. 1 is bound by the Master Facility Agreement dated 19th January, 2020 executed between SREI Equipment Finance Limited and the respondent no. 1 with regard to the financial assistance given by SREI to the respondent no. 1 of Rs. 6,72,60,000/-. The Master Facility Agreement was thereafter assigned by SREI to the petitioner in satisfaction of SREI’s dues of Rs. 70,97,70,999/- to the petitioner. The assignment was made in the form of a “Settlement Agreement” executed between SREI and the petitioner on 17th July, 2021.

The Respondent raised the issue of maintainability of the application on the ground that the respondent no. 1 is not a party to the Settlement Agreement between the petitioner and SREI and that the petitioner cannot hence seek to invoke both the arbitration clauses contained in the Master Facility Agreement and the Settlement Agreement. That there is no privity of contract between the petitioner and the respondent no. 1 and thus there cannot be a composite reference and that the petitioner has only been given the collection rights in respect of the receivables and disputes that the Master Facility Agreement had not been assigned in favour of the petitioner. It is further argued that the arbitration clause has to be specifically incorporated which has not been done in the present case. Counsel submits that a general reference to the Master Facility Agreement is not sufficient to incorporate the arbitration clause under section 7(5) of the 1996 Act.

Judgment

The High Court observed that the matter involves two agreements to which SREI is the common party but is not a party to the present application. Both agreements have independent arbitration clauses. The court held that there is no arbitration agreement between the petitioner and the respondent no. 1 which can form the basis of a section 9 application. The petitioner therefore seeks to make out a case for a composite reference on the strength of the two agreements being interlinked by reason of the petitioner stepping into the shoes of SREI in terms of the security and receivables forming the substance of the Master Facility Agreement executed between SREI and the respondent no. 1.

The court said that Section 7(5) of the Act lays down the statutory position with regard to incorporation of an arbitration clause by reference. Section 7(5) intends to link the contract without the arbitration clause to the document containing the arbitration clause subject to the contract being in writing and the reference in the contract to the arbitration clause in the document makes the arbitration clause a part of the contract. The idea is to incorporate the arbitration clause in the “document” to the “contract” by reference so that the arbitration clause is incorporated in the contract and becomes part thereof.

The above presumes that the reference to the contract is clear and reflects the intention of the parties to be bound by the arbitration clause which is to be incorporated into the contract. The incorporation of the arbitration clause into the contract (which does not contain the arbitration clause) would also have to be appropriate to the disputes under the contract to which the arbitration clause is incorporated and not result in repugnancy to the terms of the contract.

On a meaningful reading of sections 7(5), 2(1)(h) and 9(1) of the Act, only a party to the arbitration agreement, which clause was originally contained in the arbitration agreement or incorporated into a second document, can exercise the right to interim measures. This is in view of the fact that section 9 pre-supposes an underlying arbitration agreement and a party to that “arbitration agreement” applying to the Court for interim reliefs.

The court observed that while the Master facility Agreement allows SREI to transfer all or any of its rights, benefits or obligations under this Agreement to any person without notice or permission from the Borrower, the question is whether the settlement agreement is a proper deed of assignment. 

The court agreeing with the Respondents held that it is not so.  First unlike what was envisaged through the Section 7(5), both the Master and Settlement agreements had separate arbitration clauses making them separate and distinct documents and precluding the possibility of reading the arbitration clause of the Master Agreement into the Settlement Agreement. Further, a careful reading of the Settlement Agreement executed between the petitioner and SREI on 17th July, 2021 makes it clear that SREI gave the petitioner only the collection rights with respect to the receivables. The Settlement Agreement does not provide for assignment of the Master Facility Agreement of 19th January, 2020 or incorporation of the arbitration clause in the Master Facility Agreement to the Settlement Agreement by reference or otherwise or at all. To repeat, there is no special reference indicating a mutual intention on the part of the petitioner, SREI and the respondent no. 1 to incorporate the arbitration clause from the Master Facility Agreement to the Settlement Agreement. A general reference to the Master Facility Agreement is not sufficient to incorporate the arbitration clause.

Comments

Most viewed this month

The recovery of vehicles by the financier not an offence - SC

Special Leave Petition (Crl.) No. 8907  of 2009 Anup Sarmah (Petitioner) Vs Bhola Nath Sharma & Ors.(Respondents) The petitioner submitted that  respondents-financer had forcibly taken away the vehicle financed by them and  illegally deprived the petitioner from its lawful possession  and  thus,  committed  a crime. The complaint filed by the petitioner had been  entertained  by  the Judicial Magistrate (Ist Class), Gauhati (Assam) in Complaint Case  No.  608 of 2009, even directing the interim custody of the vehicle (Maruti  Zen)  be given to the petitioner vide order dated  17.3.2009.  The respondent on approaching the Guwahati High  Court against this order, the hon'ble court squashed the criminal  proceedings  pending   before  the  learned Magistrate. After hearing both sides, the Hon'ble Supreme Court decided on 30th...

Vanishing promoters and languishing shareholders

Over Rs 60,000 crore of shareholders’ wealth is stuck in 1,450 companies suspended by the stock exchanges. More importantly, near 100 per cent pledging of promoter holding appears to be common in many of these companies. This, almost rules out any chance of the companies bouncing back. The suspension is for non-compliance of the listing norms. Vanishing Companies - Definition As per the definition stipulated by SEBI, any listed company, which raised moneythrough initial public offer and, thereafter, stopped operations, did not file returnseither with the RoC or SEBI and did not exist on the registered premises wastermed as vanishing.There are provisions under Companies Act under which companies are termedvanishing companies on satisfying certain conditions. it is provided a companywould be deemed to be a vanishing company, if it satisfies all the conditions given below : a) Failed to file returns with Registrar of Companies (ROC) for a period of two years; b) Failed to fil...

Property can be sold on power of attorney - Delhi High Court

As reported in the Hindusthan Times on 5th May:-  http://www.hindustantimes.com/India-news/NewDelhi/Property-can-be-sold-on-power-of-attorney/Article1-1054964.aspx In a judgment that will benefit lakhs of Delhi residents living in co-operative housing societies and DDA flats, the Delhi High Court has quashed a Delhi government circular banning property sale in the Capital through general power of attorney (GPA). The court found that the directions in the circular, issued by the revenue department on April 27 last year, were contrary to the Supreme Court judgment dated October 11, 2011. The HC order will increase the number of saleable properties in Delhi and could bring down the value of freehold properties. According to realty watchers, on an average, around 20% of properties are registered through GPA transfers — a common way of selling leasehold properties and those that don’t have a clear title. The judgment came on a petition filed by a company, Pace Developers and ...