Skip to main content

Reference in a contract to a document containing an arbitration clause must be clear and unambiguous

Cause Title : Kobelco Construction Equipment India Private Limited vs. Lara Mining & Anr., AP 181 of 2023, Calcutta High Court

Date of Judgment/Order : 11.08.2023

Corum : Hon’ble Justice Moushumi Bhattacharya

Citied: 

  1. Duro Felguera, S.A. vs. Gangavaram Port Limited; (2017) 9 SCC 729
  2. Inox Wind Limited vs. Thermocables Limited; (2018) 2 SCC 519
  3. M.R. Engineers and Contractors Private Limited vs. Som Datt Builders Limited; (2009) 7 SCC 696
  4. Sea Trade Maritime Corpn. v. Hellenic Mutual War Risks Assn. (Bermuda) Ltd. No. 2; 2006 EWHC 2530
  5. Chloro Controls India Private Limited v Severn Trent Water Purification Inc. ; (2013) 1 SCC 641
  6. Ameet Lalchand Shah vs Rishabh Enterprises; (2018) 15 SCC 678
  7. Tantia Constructions Limited vs. Mather and Platt Pumps Limited in AP No. 72 of 2023

Background

The Arbitration Petitions have been filed under section 9 of The Arbitration and Conciliation Act, 1996 by the petitioner seeks an injunction on the respondent no 1 from dealing with or disposing of the assets under a Master Facility Agreement dated 19th January, 2020 and a Settlement Agreement dated 17th July, 2021.

The Petitioner submitted that the respondent no. 1 is bound by the Master Facility Agreement dated 19th January, 2020 executed between SREI Equipment Finance Limited and the respondent no. 1 with regard to the financial assistance given by SREI to the respondent no. 1 of Rs. 6,72,60,000/-. The Master Facility Agreement was thereafter assigned by SREI to the petitioner in satisfaction of SREI’s dues of Rs. 70,97,70,999/- to the petitioner. The assignment was made in the form of a “Settlement Agreement” executed between SREI and the petitioner on 17th July, 2021.

The Respondent raised the issue of maintainability of the application on the ground that the respondent no. 1 is not a party to the Settlement Agreement between the petitioner and SREI and that the petitioner cannot hence seek to invoke both the arbitration clauses contained in the Master Facility Agreement and the Settlement Agreement. That there is no privity of contract between the petitioner and the respondent no. 1 and thus there cannot be a composite reference and that the petitioner has only been given the collection rights in respect of the receivables and disputes that the Master Facility Agreement had not been assigned in favour of the petitioner. It is further argued that the arbitration clause has to be specifically incorporated which has not been done in the present case. Counsel submits that a general reference to the Master Facility Agreement is not sufficient to incorporate the arbitration clause under section 7(5) of the 1996 Act.

Judgment

The High Court observed that the matter involves two agreements to which SREI is the common party but is not a party to the present application. Both agreements have independent arbitration clauses. The court held that there is no arbitration agreement between the petitioner and the respondent no. 1 which can form the basis of a section 9 application. The petitioner therefore seeks to make out a case for a composite reference on the strength of the two agreements being interlinked by reason of the petitioner stepping into the shoes of SREI in terms of the security and receivables forming the substance of the Master Facility Agreement executed between SREI and the respondent no. 1.

The court said that Section 7(5) of the Act lays down the statutory position with regard to incorporation of an arbitration clause by reference. Section 7(5) intends to link the contract without the arbitration clause to the document containing the arbitration clause subject to the contract being in writing and the reference in the contract to the arbitration clause in the document makes the arbitration clause a part of the contract. The idea is to incorporate the arbitration clause in the “document” to the “contract” by reference so that the arbitration clause is incorporated in the contract and becomes part thereof.

The above presumes that the reference to the contract is clear and reflects the intention of the parties to be bound by the arbitration clause which is to be incorporated into the contract. The incorporation of the arbitration clause into the contract (which does not contain the arbitration clause) would also have to be appropriate to the disputes under the contract to which the arbitration clause is incorporated and not result in repugnancy to the terms of the contract.

On a meaningful reading of sections 7(5), 2(1)(h) and 9(1) of the Act, only a party to the arbitration agreement, which clause was originally contained in the arbitration agreement or incorporated into a second document, can exercise the right to interim measures. This is in view of the fact that section 9 pre-supposes an underlying arbitration agreement and a party to that “arbitration agreement” applying to the Court for interim reliefs.

The court observed that while the Master facility Agreement allows SREI to transfer all or any of its rights, benefits or obligations under this Agreement to any person without notice or permission from the Borrower, the question is whether the settlement agreement is a proper deed of assignment. 

The court agreeing with the Respondents held that it is not so.  First unlike what was envisaged through the Section 7(5), both the Master and Settlement agreements had separate arbitration clauses making them separate and distinct documents and precluding the possibility of reading the arbitration clause of the Master Agreement into the Settlement Agreement. Further, a careful reading of the Settlement Agreement executed between the petitioner and SREI on 17th July, 2021 makes it clear that SREI gave the petitioner only the collection rights with respect to the receivables. The Settlement Agreement does not provide for assignment of the Master Facility Agreement of 19th January, 2020 or incorporation of the arbitration clause in the Master Facility Agreement to the Settlement Agreement by reference or otherwise or at all. To repeat, there is no special reference indicating a mutual intention on the part of the petitioner, SREI and the respondent no. 1 to incorporate the arbitration clause from the Master Facility Agreement to the Settlement Agreement. A general reference to the Master Facility Agreement is not sufficient to incorporate the arbitration clause.

Comments

Most viewed this month

Partition proceedings are vitiated even if single co-sharer is not made party or is not served in accordance with law

Cause Title :  Bhagwant Singh vs  Financial Commissioner (Appeals) Punjab, Chandigarh,  CWP-2132-2018 (O&M), High Court Of Punjab & Haryana At Chandigarh Date of Judgment/Order : 31.08.2022 Corum : Hon’ble Mr. Justice Sudhir Mittal Background A large parcel of land was owned by the Nagar Panchayat. Thereafter, some of the co-sharers sold their shares to third parties including the petitioners herein. On 22.11.1995, respondents No.3 to 5 filed an application for partition of the land. The petitioners were not impleaded as parties.  On completion of proceedings, sanad was issued on 28.08.1996. Vide two separate sale deeds dated 28.05.2008 respondents No.3 and 5 sold some portion in favour of respondent No.6 and 7. These respondents sought implementation of the sanad resulting in issuance of warrants of possession dated 05.06.2008. Allegedly, it was then that the petitioners realized that joint land had been partitioned and that proceedings h...

Power of Attorney holder can also file cheque bounce cases: Supreme Court

The Supreme Court has held that a criminal complaint in a cheque bounce case can be filed and pursued by a person who holds a power of attorney (PoA) on behalf of the complainant. A three-judge bench headed by Chief Justice P Sathasivam gave the "authoritative" pronouncement on the issue, referred to it by a division bench in view of conflicting judgements of some high courts and the apex court. "We are of the view that the power of attorney holder may be allowed to file, appear and depose for the purpose of issue of process for the offence punishable under Section 138 of the Negotiable Instruments Act (which deals with cheque bounce cases)," the bench, also comprising justices Ranjana Prakash Desai and Ranjan Gogoi, said. The bench, in its judgement, said, "...we clarify the position and answer the questions in the following manner: "Filing of complaint petition under Section 138 of Negotiable Instruments Act through PoA holder is perfectly legal...

Christian who reconverts as Hindu SC will get quota benefits

Amid the controversy over “ghar wapsi”, the Supreme Court on Thursday ruled that a person who “reconverts” from Christianity to Hinduism shall be entitled to reservation benefits if his forefathers belonged to a Scheduled Caste and the community accepts him after “reconversion”. Citing articles by B R Ambedkar and James Massey, and reports by Mandal Commission and Chinappa Commission, the court said: “There has been detailed study to indicate the Scheduled Caste persons belonging to Hindu religion, who had embraced Christianity with some kind of hope or aspiration, have remained socially, educationally and economically backward.” The bench of Justices Dipak Misra and V Gopala Gowda held that a person shall not be deprived of reservation benefits if he decides to “reconvert” to Hinduism and adopts the caste that his forefathers originally belonged to just because he was born to Christian parents or has a Christian spouse. Expanding the scope of a previous Constitution benc...