Skip to main content

Builder has to pay compensation if project is delayed

Building projects are often delayed due to disputes between a builder, land owner and developer. Builders try to term these as force majeure, which means due to circumstances beyond their control, to avoid being held liable for deficiency in service. In a recent ruling, the National Commission has held that such disputes cannot be termed force majeure, and a consumer would be entitled to claim a refund along with interest and compensation when the builder is unable to complete the housing project in time. However, a builder can neither unilaterally extend the date of possession nor insist on allotting alternate flat or plot to escape refunding the amount.

Shahin Mulla wanted to purchase a residential unit in "Amar Prem", a housing project in Goa, to be developed by Utopia Projects. The entire consideration of Rs 30 lakh was paid in two instalments of Rs 15 lakh each.

The agreement for construction and sale was executed thereafter on February 24, 2012. It stipulated that possession would be given by September 2013, but the builder would be entitled to a grace period of four months, i.e. till January 2014.

When Mulla visited the site in August 2013, she found that even the foundation had not been laid. She got a legal notice issued to the builder, which was ignored. So she filed a complaint before the Goa State Commission.

The builder contested the complaint, explaining that they had been assigned development rights by RPC Builders and Developers, who had later committed various breaches and were also demanding extra payment for the property. As a result of the dispute, work could not commence. The builder termed the dispute as force majeureand not due to any wilful default. Utopia Projects also pointed out that the complaint was premature as it had been filed prior to January 2014, which was the date of possession inclusive of the grace period.

The state commission observed that the agreement provided that in case of any delay beyond the grace period, the builder would pay the purchaser a monthly compensation at Rs 50 per sq.ft. The defence of force majeure cannot be invoked as the agreement had not been terminated due to inability to perform it.

The state commission concluded that there was deficiency in service and ordered the builder to refund the amount of Rs 30 lakh along with 5% interest from the date of payment of each instalment till the extended date of possession. For the delay, the commission directed payment of a monthly compensation of Rs 50 per sq. ft. from February 1, 2014 till the date of payment. For mental agony, a further amount of Rs 1 lakh was awarded, which would carry 9% interest if not paid within 30 days.

Utopia Projects appealed to the National Commission, contending that the company had formulated a revised schedule, but Mulla was not willing to accept it. In its judgment of April 1, 2015 delivered by M Shreesha for the Bench along with Justice DK Jain and Vinay Kumar, the National Commission held that a consumer is not concerned with the internal disputes between the landowner, developer or contractor. A builder cannot take shelter by wrongly terming internal disputes as force majeure. It ruled that Mulla was well within her rights to demand possession within the stipulated time or else seek a refund along with compensation. Accordingly, the National Commission rejected the builder's appeal, holding that the state commission had rightly allowed Mulla's claim.

Article referred: http://timesofindia.indiatimes.com/city/mumbai/Builder-has-to-pay-compensation-if-project-is-delayed/articleshow/47143531.cms

Comments

Most viewed this month

Deposit Of Minimum 20% Fine/Compensation U/s 148 NI Act Mandatory

In OP(Crl.).No.348 OF 2019, T.K.SAJEEVAN vs FRANCIS T.CHACKO, the appeal was filed against the order of the lower court to deposit 25% of the fine before filling of appeal. The appellant argued that the deposit introduced through the Section 148 of the NI Act after amendment was directory in nature as it used the term 'may' while mentioning the issue of deposit. The Kerala High Court however disagreeing held that in view of the object of the Legislature while incorporating Section 148 into N.I. Act, the word 'may' will have to be read as 'shall'. The imposition of payment contemplated under Section 148 N.I. Act cannot be restricted to some prosecutions and evaded in other prosecutions. Since the amount directed to be deposited being compensation, undoubtedly, it is liable to be ordered to be deposited irrespective of the nature of the prosecution. Therefore, the word 'may' can only be taken to have the colour and meaning of 'shall' and there

NCLT - Mere admission of receipt of money does not qualify as a financial debt

Cause Title : Meghna Devang Juthani Vs Ambe Securities Private Limited, National Company Law Tribunal, Mumbai, CP (IB) No. 974/MB-VI/2020 Date of Judgment/Order : 18.12.2023 Corum : Hon’ble Shri K. R. Saji Kumar, Member (Judicial) Hon’ble Shri Sanjiv Dutt, Member (Technical) Citied:  Carnoustie Management India Pvt. Ltd. Vs. CBS International Projects Private Limited, NCLT Swiss Ribbons Pvt. Ltd. & Anr vs. Union of India & Ors. (2019) Sanjay Kewalramani vs Sunil Parmanand Kewalramani & Ors. (2018) Pawan Kumar vs. Utsav Securities Pvt Ltd 2021 Background Application was filed under section 7 of the Insolvency and Bankruptcy Code, 2016 alleging loan of Rs, 1.70 cr is due. The Applicate identified herself as the widow and heir of the lender but could not produce any documents proving financial contract between her Late husband and the CD but claimed that the CD has accepted that money was received from her husband. The applicant subsequently filed rejoinder claiming the debt t

Jurisdiction of consumer forum is not ousted even if the other party has filed suit on the same matter in Civil Court

In Yashwant Rama Jadhav v. Shaukat Hussain Shaikh, First Appeal No. 1229 of 2017, decided on 18.11.2017,  the grievance of the petitioner before the National Consumer Disputes Redressal Commission was that appellants/complainants had entered into agreements with the respondents for purchase of residential flats, which the respondents were to construct and despite paying the substantial amount to the respondents, the construction of the flats had not been completed. The State Commission dismissed the complaints and ruled in favor of respondents against which the appellants approached the National Commission. The NCDRC held that Section ‘3’ of the Consumer Protection Act, to the extent it is relevant provides that the provisions of the Act shall be in addition and not in derogation of the provisions of any other law for the time being in force. Thus the remedy available under the Consumer Protection Act is an additional remedy, which Parliament has made available to a consumer. Even